HomeMy WebLinkAbout1991-10-09 Council MinutesROAD COMMITTEE OCTOBER 9th, 1991
The Road Committee of Harold Mueller, Lawrence Hogg, and John
C. Jeffery met in the morning of Wednesday, October 9th, 1991
The following items were reviewed.
1 Crossroads Project - South of 28, 29, 30 in 34 -25 -4
Okay to write off. 4 3 mile project General clean up
required. Rocks to be picked and rock pits closed
Rip Rap required for some culverts
2 Kerns Project - not complete as yet
3 SR 587 Project - Recommend give Len McCook M D rock picker
for one day to pick rocks in the Johnson borrow pit area
Note area has been picked twice already - which exceeds
terms of backsloping borrow pit agreement
4. SR 582 - not complete
5 Neil Silver stock pile site - SW 16-34 -24 -4 - not reclaimed
as yet
6. SR 583 - not complete
7 Flores Molendyk - Road East of 26- 32 -26 -4 - recommend a
cat try to flatten out the grade in hill and made small
ditch to cary water Project must be done in spring and
regrassed as soon as possible Try to keep as flat as
possible Contact Bob Larsen re small amount of cat
work while our machine is there
8 Sunnyslope - recommend no exit signs be placed on both
streets Clean up required, but Swalwell needs clean
up first.
9. Reviewed Blackie Pit haul road access and recommend
we continue to use Ken Lowen Land - through his garden
and remove trees as necessary We have paid him for
access and see no reason to pay another party for
different access Also Ken is agreeable to us going
through his garden etc
Note This recommendation with discussed with
Oris, Otto and J. Finlay Code as Oris felt it was
too close to Ken's house and would create more problems
with Ken - i e dust, noise, etc. and problems with
reclamation of garden area It was agreed as follows.
Finlay Code obtained verbal consent from Gordon Taylor
and Clarence Colberg (his tenant) that the M D could make
use of the access road through his property (Ken Lowen's
access road is apparently on Mr Taylor's property). Mr
Taylor indicated he would not want any compensation
Oris advises the trucks would have to go out around the
straw bales on Mr Taylor's property and then swing back
onto the access road
1
It was also agreed Oris would have to install a texas
gate on C P rail property as Jack Lowen has fenced off
the area and has cattle in there Truckers will not
stop to open gates The gate will have to be removed
when the haul is finished
Pl It
B
10
11.
12
13
16.
2
ROAD COMMITTEE OCTOBER 9th, 1991
Atlantis 2 -21- 33-24 -4 - Project not complete
Tyler James - NE 8- 29 -21 -4 - recommend write another
letter to Mr James as work not done
Opinac 6- 6- 35 -24 -4 - okay to write off
Atlantis 8- 32- 34 -23 -4 - Advise Atlantis that
large loose rocks must be picked and area seeded to
grass
Vetter Bridge needs to be cleaned up - old bridge
Advise A G T cut culvert at Dale Cameron - and
must be fixed
Sailer Agreement N W 8- 34 -23 -4 - fence to be replaced
barb wire - Owner to supply 4th wire Fence to be
replaced on property line Would like share of gravel from
old road and any excess black dirt is to be stockpiled
for owner No mention of any electric fence. Was
approved by Council June 25/91